Self-levelling compound: kilograms per square metre and millimetre

Floor levelling compounds are frequently specified by a mass consumption in kilograms per square metre per millimetre of thickness. This makes the average applied depth essential: one deep depression does not describe the entire floor. The exact product is also important because different compounds allow different layer thicknesses.

Deutsche Originalfassung

Calculate your result

Use the corresponding calculator with values for your product or project. This guide cannot verify local technical rules.

Open calculator →

Step-by-step guidance

1. Assess the full floor area

Measure the zone to be levelled and identify high and low points. Work with an estimated average layer thickness, not simply the largest depth. Deep local holes can be calculated separately where appropriate.

2. Use the manufacturer’s kg/m²/mm value

Multiply the area by the average millimetres and the declared consumption rate. Ensure that the selected compound is suitable for the substrate, minimum and maximum layer thickness and intended finish.

3. Convert the result to full packs

Take the calculated kilograms, apply any justified allowance and round up to the available bag size. Separate primer, edge details and moisture protection from the compound calculation, and follow the product’s mixing instructions.

Formula

Mass (kg) = area (m²) × average depth (mm) × product consumption (kg/[m²·mm]).

Worked example

For 16 m² at an average 4 mm with an illustrative 1.6 kg/(m²·mm), the requirement is 102.4 kg. Five 25 kg bags cover that figure before further allowances.

Common mistakes

  • Using the maximum depth as the average everywhere
  • Confusing consumption per mm with consumption per cm
  • Assuming primer and substrate preparation are included in the bag quantity

Frequently asked questions

Why does average depth matter?

Total consumption depends on the actual volume over the full floor. One isolated low point cannot represent the entire area.

Will I also need a primer?

Often a system-compatible substrate preparation is required. Follow the product data for the substrate and levelling compound.

Example values are planning assumptions, not binding product specifications. Check local rules, supplier information and professional guidance. Electrical examples do not establish a safe installation or protection.